Data Entry/Review module

 

Changing the status of SDV marks

  1. Open the SDV Browser. How to do this...

  2. Right click on an SDV and select Set the SDV Status to... The status change window is displayed beneath the browser.

  3. Enter any text you wish to enter.

  4. Click OK. The status of the SDV will be changed as specified.

Changing the status of multiple question SDVs

You can change the status of all question SDVs on a single eForm from Planned to Done in one go.

  1. Open the schedule.

  2. Right click on the eForm containing the SDVs you wish to change.

  3. Select Change all Planned question SDVs to Done.

  4. Click Yes to confirm the change.

 

If data changes after an SDV mark has been set to Done, the SDV mark will be automatically reset to Planned, to allow re-verification of the data.

The SDV status of an object (subject, visit, eForm) will only be Done if the object itself has a Done SDV and not if it only contains other objects with Done SDVs. For example, an eForm may contain questions which each have Done SDVs. Unless the eForm itself also has a Done SDV, the Done icon will not be displayed on the schedule and in the browser for the eForm.

SDV icons in the schedule

If a visit, subject or eForm contains one or more items with Planned or Queried SDV marks, the relevant status icon will be displayed at all levels but once the SDV mark has been changed to Done, the status icon will only be displayed for the individual object.

 

Planned

SDV is yet to be done

Queried

There is some problem with the data verification

Done

Source data has been verified satisfactorily

 

Cancelled

The SDV mark is no longer required

 

 

 

Related Topics

About SDV marks

Searching for SDV marks